Wednesday, November 18th 2020 – The Great House Extension Project (Days 87 – 89) Monday was all about the “chimney breast” and its construction. Dave turned up single-handed, and we spent a good hour discussing what we wanted, pondering the size of the electric fire we have bought, and trying to work out how to…
Category: The Great House Extension Project
Home 2020 – The Great House Extension Project (Days 77 – 86)
Friday, November 13th 2020 – The Great House Extension Project (Days 77 – 86) It’s been one hell of a two weeks. It started on 2nd November when the plasterer was due to start. Except that the plasterer couldn’t come because he was busy getting a Covid-19 test, which would take at least two days…
Home 2020 – The Great House Extension Project (Days 45 – 76)
Friday, October 30th 2020 – The Great House Extension Project (Days 45 – 76) And lo, we have a roof! And one or two new walls. And a floor. The start of October saw the removal men appear and empty out the lounge and dining room, the bigger of the spare bedrooms, and our bedroom,…
Home 2020 – The Great House Extension Project (Days 8 – 44)
Wednesday, September 16th 2020 – The Great House Extension Project (Days 8 – 44) I would have liked to keep on blogging the process of the dreaded extension build we’re in the middle of but things went badly wrong in mid-September when Lynne went out for a walk to avoid the cleaners (as part of…
Home 2020 – The Great House Extension Project (Day 6)
Monday, July 27th 2020 – The Great House Extension Project (Day 6) So, the tree is now gone, Rob, the Structural Engineer, has drawn up the necessary plans for dealing with the remnants (the roots mostly) and Mal the builder has been back for another look at the site now it no longer has a…
Home 2020 – The Great House Extension Project (Days 4 & 5)
Thursday/Friday, July 23rd/24th 2020 – The Great House Extension Project (Days 4 & 5) On Thursday nothing much happened, but on Friday the offending tree went. If I’d left it to Jim (the architect) the gods only know how long we’d have had to wait. I didn’t, because the best man for the job is…
Home 2020 – The Great House Extension Project (Day 3)
Wednesday, July 22nd 2020 – The Great House Extension Project (Day 3) Jim, the architect turned up unexpectedly today and spent some time staring at the tree. He is still of the opinion that the tree could just go and no one will turn a hair. Later on two separate tree surgeons turned up to…
Home 2020 – The Great House Extension Project (Day 2)
Tuesday, July 21st 2020 – The Great House Extension Project (Day 2) No building whatsoever today, and no contact from anyone apart from a brief communication from the architect saying he thought we could “just cut the tree down and worry about it later” and saying that he had asked Rob, our Structural Engineer, to…
Home 2020 – The Great House Extension Project (Day 1)
Monday, July 20th 2020 – The Great House Extension Project (Day 1) Getting building work done is always stressful for the householder, no matter what level of disruption you’re expecting. A couple of years back we started to plan to extend our current house to give ourselves a decent amount of space in the lounge/dining…